Construction log 03/02/2021

 글쓴이 : Oscar

Warning: Undefined array key "hitShowYN" in /home1/chsixchn/public_html/_newhome/_chboard/skin/board/r_photo/view.skin.php on line 26
조회 : 131

With the digging part over and the footings and beams assambly at a 95%, we are now cleaning off the dirt that resulted from the digging, this to start placing all the iron structure in the trench tomorrow. The plan is to complete installing the iron structure and preparing the formwork  this week, this to get ready to pour the concrete next week.